Now that the Draco OGDP application has been deemed complete by the ECMC, the documents submitted with the application are available to view/download. Here, we’re taking an opportunity to analyze the submitted Form 2B Cumulative Impacts Data Identification Form and share some new information.
- Extraction plans to spend 9 weeks constructing the location, 18 weeks to drill the wells, and 23 weeks to complete the wells for Draco, for a total of 50 weeks of pre-production activities, assuming two concurrent electric drilling rigs will be used. The wells will be in production for 20 years.
- The operator estimates 158,125 diesel vehicle miles will be driven before the wells are put into production to deliver sand, pipe, and other materials to the site.
- The project will use 3.27 million pounds of proppant/sand during completions activities.
- They plan to use 12,885,000 barrels of water to frack the 26 wells at Draco, for a total of 541 million gallons of water and an average of 20.8 million gallons per well.
- They will not be recycling produced water because “the infrastructure necessary to reuse or recycle water does not exist in this area.”
- Extraction plans to plug and abandon 22 wells at 18 locations, as well as removing 24 oil tanks and 13 produced water tanks.